Wednesday, October 31, 2012

Moving Dirt

All that remains of the Pro Shop.

A pile of rubble that was the clubhouse.
Rubble being hauled away truck by truck.



The original flagpole was removed and stored.

Dirt work started this past Monday. Topsoil is stockpiled prior to grading activities. This area is left of the 1st hole.

D8 Cat pushing topsoil.

Stockpiling in front of 11 green.



A view from the 18th tee.

Friday, October 26, 2012

Demolition Day

The Pro Shop and Clubhouse buildings were knocked down today. It took about one hour to level the clubhouse and even less for the Pro shop!


The first swipe!











The end product







All that remains of the Pro shop. Some of the white fence on the 1st tee still stands.
 

Wednesday, October 24, 2012

Silt Fence Everywhere



Silt fence is installed by this crew using a tractor and specialized attachment that anchors the fabric in the ground. Stakes are pounded by hand.



#6 wetland protected



#5 wetland

#2 fairway without the line of ash trees running up the left side.

Tuesday, October 23, 2012

First Post!


Over the next eighteen months, Keller GC will undergo some exciting changes and improvements both on the golf course and with a new clubhouse. I always carry a camera as I drive the property so I will have many photos to share as the project moves forward. Please check back on a regular basis as I hope to add new posts frequently.



Silt fence installation begins around 1st tee...
 

 and below the parking lot.
 



Keller staff removing old irrigation heads from fairways.
 




The general contractor for the clubhouse project has moved on site.