Monday, November 26, 2012

Progress slows

Not a lot of photo-worthy changes to share with you from the past ten days. The big news is the rough grade of the irrigation pond is complete. This week Duininck plans to begin drainage installation throughout the golf course. Richard Mandell, our golf course architect, is in town on Thursday for a site inspection and walk through.

Note: Though there are no photos of  clubhouse progress in this post, some footings were poured last Wednesday.





The current view from the 16 forward tee back towards the blue tee.
The new look from the back tee on 16.  Four feet of cut will be removed from the ridge in the center of the photo to improve sight lines.

Footings for the Pro Shop were poured this week.

Concrete pumping rig used to get concrete to the footing forms .


Pro Shop foundation.




A view across the driving range tee.


Looking out on the driving range.


This is the roughed-in version of our new irrigation pond. Once the water is removed the bottom and sides will be smoothed out in preparation for a pvc liner. The liner won't be installed until next spring.


These are sections of concrete culvert to be used as a wet well in the new irrigation pumphouse. Note the 30-inch hole in the section on the left. That section will be at the bottom of the wet well and the hole will accomodate a 30-inch intake pipe from the pond.