Heavy snow over the weekend (12+ inches). Work on the golf course may be ending shortly...we shall see. Drainage install was moving ahead full speed this past week. The wet well install was also completed last week.
Here is an article just released a few days back on the Keller project:
Minnesota's History Keller GC Getting Major Facelift
|
Adding another section to the wet well. |
|
Finished wet well. New pumphouse will sit on top of this structure. |
|
Intake pipe in position. |
|
Drainage crew working their way up 8 fairway headed towards 6 pond |
|
Drainage install in 7 fairway. |
|
A drainage run in front of 7 tee that connects to 6 pond. |
|
Drainage being installed in 14 fairway. |
|
Drainage run cut through the ridge on 14 fairway - 14 feet deep. |
|
Drainage run from 14 fwy up to 16 tee complex. |
|
Duininck Project Manager, Ahren Habicht, checking location of the pad for 16 "B" tee. |
|
A look from above at 14 fairway drainage install. |
|
Pizza party for the Duininck staff. |
|
Bill Bartodziej, Natural Resource Specialist with the Ramsey Washington Metro Watershed District, stopped by to check on the project. RWMWD will be involved in prairie and woodland restorations on the golf course in 2013. |
|
A view from the maintenance facility as fill is added to the 12 tee complex. |
|
Walls start to go up on the clubhouse. |
No comments:
Post a Comment